Kohl’s: 2101 Autumn Slate Drive, Pflugerville
Type of work: new construction
Timeline: May 1-Oct. 16
Estimated cost: $3.4 million
Scope of work: new Kohl’s department store
Pecan Central Office Park: 105 Rex Kerwin Court, Pflugerville
Type of work: new construction
Timeline: Feb. 1-Aug. 1
Estimated cost: $1.2 million
Scope of work: new construction of two single-story professional office buildings and related site work; buildings are 3,865 square feet and will total 7,730 square feet when fully completed; site is approximately 0.75 acres.
Oncor Service Center-Williamson County: 3487 CR 100, Ste. 100, Hutto
Type of work: new construction
Timeline: Dec. 15-Nov. 30
Estimated cost: $8 million
Scope of work: construction of a new single-story office building with exterior, coverage storage, and parking canopies
45 Crossing-Suite 100 Ready Spaces: 2700 Louis Henna Blvd., Ste. 100, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 1-April 1
Estimated cost: $325,000
Scope of work: new interior build out in an existing shell building
Take 5 Hutto: Chris Kelley Blvd., Hutto
Type of work: new construction
Timeline: Jan. 17-April 29
Estimated cost: $450,000
Scope of work: new construction for a drive-thru oil change facility and site