Prosper has multiple ongoing transportation projects expected to start in 2024. Here is a quick look at some of the highlights:

Dual left turns for Coit Road and US 380

An additional left-turn lane is being added to the southbound Coit Road and US 380 intersection. Project steps include updating existing traffic signals, adding pavement, modifying striping and signage, and restoring vegetation and irrigation once construction ends, according to the project dashboard.
  • Timeline: early 2024-summer 2024
  • Cost: $300,000
  • Funding source: town of Prosper
Coleman Street lane additions

This project will add the next two out of four lanes to Coleman Street between Prosper Trail and Prosper High School. Project details include adding a curb and gutter, some underground drainage improvements and median landscape improvements.
  • Timeline: winter 2024-summer 2026
  • Cost: $3.77 million
  • Funding source: town of Prosper
Coleman Street improvements

Also tackling Coleman Street, this project focuses on improving an existing rural two-lane road between Gorgeous Road and Prosper Trail by expanding it to four lanes. Other aspects of the project include adding a curb and gutter, underground drainage improvements, and median landscape improvements.
  • Timeline: winter 2024-summer 2026
  • Cost: $6.65 million
  • Funding source: town of Prosper
First Street improvements


As one of many First Street-focused projects, construction will focus on improving an existing rural two-lane road between the Dallas North Tollway and Coleman Street by expanding it to a divided, arterial four-lane road. Other aspects of the project include adding a curb and gutter, underground drainage improvements, adding a 12-inch water line and median landscape improvements.
  • Timeline: summer 2024-spring 2026
  • Cost: $21.79 million
  • Funding source: town of Prosper