Learn more about transportation projects in the Plano area that are currently underway, including Parker Road construction and upcoming Custer Road closures, according to the city's community investment program. This list is not comprehensive.

Upcoming projects:

1. Southwest Plano residential street repairs
  • Project: Plano is working to repair neighborhood infrastructure, including residential concrete streets, alleys, sidewalks and ramps.
  • Update: Plano City Council approved a $3.31 million contract at an Oct. 27 meeting for repairs in the area bounded by Decator Drive, Park Boulevard, Tulane Drive and Preston Ridge Trail. Construction is expected to begin in early January.
    • Timeline: January 2026-TBD
    • Cost: $3.31 million
    • Funding source: city of Plano
Ongoing projects:

2. Custer Road waterline replacement
  • Project: The North Texas Municipal Water District is currently working to replace an aging pipeline along Custer Road.
  • Update: More than a third of the 9,100-foot pipeline has been installed, according to a city news release. All northbound lanes of Custer Road between Westridge Drive and Grandview Drive will be closed Jan. 5-26. Traffic will be shifted to the southbound lanes of Custer Road, according to the release.
    • Timeline: February 2025-October 2026
    • Cost: $18 million
    • Funding source: North Texas Municipal Water District
3. 15th Street paving and waterline reconstruction
  • Project: The project involves the removal and replacement of pavement, sidewalks and water lines along 15th Street from Municipal Avenue to Jupiter Road.
  • Update: construction is underway.
    • Timeline: August 2025-March 2027
    • Cost: $6.939 million
    • Funding source: city of Plano
4. Park Boulevard water rehabilitation project
  • Project: the two-phase project, stretching from Preston Road to Plano’s east city limits combined, is working to replace the waterlines running under Park Boulevard.
  • Update: Water line construction wrapped up in December, but remaining work on pavement and larger cleanup items are expected to continue through the end of January, Public Works CIP Manager Drew Zaeske said.
    • Timeline: September 2024-January 2025
    • Cost: $9.58 million
    • Funding source: city of Plano
5. Custer Road asphalt overlay
  • Project: crews are undergoing the arterial overlay process which aims to expand the road’s lifespan.
  • Update: arterial concrete repairs on Custer Road from Hedgcoxe Road to Spring Creek Parkway are underway.
    • Timeline: August 2025-October 2026
    • Cost: $1.63 million
    • Funding source: city of Plano
6. Coit Road asphalt overlay
  • Project: crews are working on arterial concrete overlays.
  • Update: arterial concrete repairs on Coit Road from SH 190 to Parker Road are underway.
    • Timeline: July 2025-July 2026
    • Cost: $1.611 million
    • Funding source: city of Plano
7. McDermott Road asphalt overlay
  • Project: crews are working on arterial concrete overlays.
  • Update: arterial concrete repairs on McDermott Road from Preston Road to Coit Road are underway.
    • Timeline: July 2025-March 2026
    • Cost: $900,000
    • Funding source: city of Plano
8. Plano Parkway sewer improvements
  • Project: Plano is working to make sewer improvements along Plano Parkway to increase sewer capacity for current and future development in the area.
  • Update: Several lanes along Plano Parkway will see closures as construction continues.
    • Timeline: July 2025-spring 2027
    • Cost: $16.1 million
    • Funding source: city of Plano
Completed projects:

9. Communications Parkway asphalt overlay
  • Project: crews are working on arterial concrete overlays.
  • Update: arterial concrete repairs on Communications Parkway from Legacy Drive to Chapel Hill Boulevard are expected to wrap up in December.
    • Timeline: January 2025-December 2025
    • Cost: $1.53 million
    • Funding source: city of Plano
10. Parker Road asphalt overlay
  • Project: Crews are working on arterial concrete overlays.
  • Update: Arterial concrete repairs on Parker Road from Country Place Road to Independence Parkway were substantially completed Dec. 4 with minor items remaining.
    • Timeline: August 2024-winter 2026
    • Cost: $4.37 million
    • Funding source: city of Plano