Several power, water and energy relocations are taking place this week in Colleyville along SH 26 in preparation for the next phase of TxDOT's reconstruction project, according to a city press release.
Water line relocations
The outside northbound lane of SH 26, from Brown Trail to Bransford Road (just south of the Texaco station), will be closed from 9:00 a.m. to 4:00 p.m. this week so crews can install a new waterline.
A new water line will also be installed in the 4500 block of SH 26 (near Braum's). For that line, crews will bore below SH 26 to allow for the installation. No impact to traffic is anticipated.
Atmos Energy line relocations
Atmos will be relocating gas lines from Industrial Boulevard to Oak Pointe Drive this week. There will be no lane closures and any impact to traffic in the area should be minimal. All businesses affected by the relocation work have been notified and the city is helping to schedule the work to minimize the impact to those businesses. Starting today, Industrial Boulevard will be reduced to one way, in and out, from 9 a.m. to 4 p.m.; however, the road will not be completely closed.
Atmos will continue to bore lines along SH 26 from Church Street to just north of Thompson Terrace. There should be no impact to traffic in that area.
Oncor power line relocations
Oncor will continue to move overhead power lines located along the east side of SH 26 from Brown Trail to Glade Road. There should be no impact to traffic in that area.
Time Warner relocations
On Monday, Time Warner began moving overhead cable on the east side of SH 26-southbound from Tennison Parkway to Tarrant Lane.