The city of Colleyville has announced the temporary relocation of utility poles, which resulted in obstruction on some sidewalks along Glade Road. This work is to allow room for construction of new roundabouts to continue. Colleyville City Council agreed April 7 to pay Ed Bell Construction Company $14.2 million for work on Glade Road. The city will upgrade the condition of 1.5 miles of the road from SH 26 to Pool Road.
Timeline: 24-30 months from start of construction in July
Cost: $14.2 million
Funding source: city of Colleyville