Upcoming
1. New traffic signal addition
Project: The traffic signal will be new at the Eldorado Parkway and Custer Star Addition intersection.
Update: The project is in the design phase, which is projected to end in Quarter 2 of 2025. Once the design phase is complete, it will move to construction.
- Timeline: Q2 2025-Q4 2025
- Cost: $335,000
- Funding source: city of Frisco
Project: A roundabout will be added to the Ohio Drive and Wade Boulevard intersection.
Update: The project is currently in the planning phase. The design phase will follow before construction can begin.
- Timeline: Q3 2026-Q3 2027
- Cost: $4 million
- Funding source: city of Frisco
Project: The road will be widened from Lebanon Road to Stonebrook Parkway and from Stonebrook Parkway from Legacy Drive to 4th Army Drive. The roadway will be widened and reconstructed.
Update: The project is in the design phase, which will wrap up next year before construction can start.
- Timeline: Q3 2026-Q4 2027
- Cost: $15 million
- Funding source: city of Frisco
Project: Lebanon Road will be widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive.
Update: The project is expected to go to bid in mid-2025 once the design phase, its current phase, is completed.
- Timeline: Q2 2025-Q4 2027
- Cost: $26.5 million
- Funding source: city of Frisco
Project: Meadow Hill Drive and a portion of North County Road will be reconstructed.
Update: The project is in the design phase which is set to wrap in mid-2025 before it goes to construction.
- Timeline: Q2 2025-Q3 2026
- Cost: $3.7 million
- Funding source: city of Frisco
6. Hillcrest Road construction
Project: The project will construct a four-lane divided roadway from Panther Creek Parkway to PGA Parkway.
Update: The project is expected to wrap later this year.
- Timeline: Q1 2024-Q3 2025
- Cost: $5.99 million
- Funding source: city of Frisco
Project: The Panther Creek Parkway construction is currently underway. It will construct a new six-lane divided roadway from the Dallas North Tollway to Preston Road.
Update: The project is under construction and is in its last few months of work.
- Timeline: Q1 2024-Q4 2025
- Cost: $56.4 million
- Funding source: city of Frisco, Collin County
Project: The roadway will run from Dallas Parkway to Panther Creek Parkway. It will be a divided six-land roadway.
Update: The project is under construction, but it was expected to be completed at the end of 2024, according to the city’s capital improvement website. The road will be the main road to the new Universal Kids Resort, which is expected to open in 2026.
- Timeline: Q3 2023-TBD
- Cost: $12.94 million
- Funding source: city of Frisco
Project: Main Street will be turned into a pedestrian plaza along with Fourth Street as part of a Rail District redevelopment project by the city.
Update: The road is still under construction and lane changes continue through the Rail District.
- Timeline: Q1 2024-Q4 2025
- Cost: $20.54 million
- Funding source: city of Frisco
Project: A new traffic signal will be added to the intersection at Eldorado Parkway and Research Road.
Update: The project is under construction and expected to wrap later this year.
- Timeline: Q4 2024-Q3 2025
- Cost: $250,000
- Funding source: city of Frisco