Construction has begun on the first phase of a Rockhill Parkway extension from Mahard Parkway to just west of Legacy Drive. The new six-lane, divided roadway project also includes the installation of a water line. The next phase of the project will be the northern border for the future Professional Golfers’ Association of America’s development.
Timeline: September 2019-September 2020 (Mahard Parkway to west of Legacy Drive), November 2019-June 2020 (Teel Parkway to west of Legacy Drive)
Cost: $12.3 million (Mahard Parkway to west of Legacy Drive), $10 million (Teel Parkway to west of Legacy Drive)
Funding source: city of Frisco