This two-part Texas Department of Transportation project widens FM 2978 from two lanes to four, stretching from Hufsmith-Conroe Road to FM 1488 in Magnolia. As of mid-June, Segment 1—which runs from Hufsmith-Conroe to south of Dry Creek near Hardin Store Road—was 44% complete, and Segment 2—which runs from FM 1488 to south of Dry Creek—was 27% complete.
Timeline: January 2018-fourth quarter 2019 (Segment 1), September 2018-second quarter 2021 (Segment 2)
Cost: $34.2 million
Funding source: TxDOT