The accepted bid price was $260,936, according to meeting documents. The estimated completion time in calendar days for the project is listed as 60 days.
The details
The project was previously approved as part of the county’s 2020 mobility bond, which provided $500,000 for the project.
According to the 2020 mobility projects list, the scope of work for the project includes:
- Safety improvements
- Curb radius reductions
- Reduce pedestrian crossing length
- Speed reduction