CMAQ 4-Phase 2D will include traffic signal modifications and intersection improvements along the Hwy. 249 frontage road between Antoine and Spring Cypress roads. Construction bids were awarded March 6, and the notice to proceed with construction was issued July 29.

Timeline: July 29, 2019-January 2022
Cost: $3.61 million
Funding sources: Harris County Precinct 4, TxDOT

Share this story
COMMENT

Leave A Reply

Hannah Zedaker
Born and raised in Cypress, Texas, Hannah Zedaker graduated from Sam Houston State University in 2016 with a bachelor's degree in mass communication and a minor in political science. She began as an intern with Community Impact Newspaper in 2015 and was hired upon graduation as a reporter for The Woodlands edition in May 2016. In January 2019, she was promoted to serve as the editor of the Spring/Klein edition where she covers Spring ISD and Harris County Commissioners Court, in addition to business, development and transportation news.
Back to top