Harris County Precinct 4, TxDOT to improve Hwy. 249 corridor between Antoine, Spring Cypress roads

CMAQ 4-Phase 2D will include traffic signal modifications and intersection improvements along the Hwy. 249 frontage road between Antoine and Spring Cypress roads. Construction bids were awarded March 6, and the notice to proceed with construction was issued July 29.

Timeline: July 29, 2019-January 2022
Cost: $3.61 million
Funding sources: Harris County Precinct 4, TxDOT
By Hannah Zedaker

Editor, Spring/Klein & Lake Houston/Humble/Kingwood

Hannah joined Community Impact Newspaper as a reporter in May 2016 after graduating with a degree in journalism from Sam Houston State University in Huntsville, Texas. In March 2019, she transitioned to editor of the Spring/Klein edition and later became the editor of both the Spring/Klein and Lake Houston/Humble/Kingwood editions in June 2021. Hannah covers education, local government, transportation, business, real estate development and nonprofits in these communities. Prior to CI, Hannah served as associate editor of The Houstonian, interned with Community Impact Newspaper and spent time writing for the Sam Houston State University College of Fine Arts and Mass Communication and The Huntsville Item.