Gosling Road widening-segment 1 Segment 1 of Gosling Road is under construction between Spring Stuebner and Mossy Oaks roads. Improvements include widening Gosling Road from a two-lane asphalt roadway to a five-lane pavement section between Spring Stuebner and the Grand Parkway, and a four-lane pavement section with a 14-foot wide median between the Grand Parkway and Mossy Oaks Road West. The construction contract was awarded to Allgood Construction on Aug. 9, and Harris County issued the notice to proceed on construction. Construction began Oct. 3. The contract allows for 360 days for completion. Timeline: Fall 2016-second quarter 2017 Cost: $8.2 million Funding sources: Harris County