1. PopStroke: 23330 Grand Circle Blvd., Katy
Type of work: new construction
Timeline: Jan. 1-July 15
Estimated cost: $4 million
2. Burlington: 529 Stockdick School Road, Katy
Type of work: new construction
Timeline: Nov. 11-Sept. 1
Estimated cost: $1.3 million
3. Enclave at Katy Bend Fort Road: Katy Fort Bend Road, Katy
Type of work: new construction
Timeline: Feb. 28, 2022-Feb. 28, 2024
Estimated cost: $41 million
4. Tamarron Recreation Center: Tamarron Point and Tamarron Parkway, Katy
Type of work: new construction
Timeline: Jan. 1-April 1
Estimated cost: $2.5 million
5. Whataburger: 9822 Gaston Road, Katy
Type of work: new construction
Timeline: Jan. 21-June 20
Estimated cost: $2.3 million