Timeline: February 2021-fourth quarter 2023
Cost: $14.69 million
Funding sources: federal, state
2. A third segment of FM 1097 is also being widened between Lake Conroe Hills Drive and Blueberry Hill. FM 1097 will be widened from two to four lanes with a continuous center turn lane. The project was 7% completed as of a June update, and the contractor has 328 working dates to finish the project, according to TxDOT.
Timeline: second quarter 2022-TBD
Cost: $14.72 million
Funding sources: federal, state