The overview
The $1.9 billion bond voters approved in 2023 consisted of projects that include eight new campuses, three additions and five major renovations.
New campuses include an elementary school in The Woodlands High School feeder zone, an elementary school in the Highway 242 corridor, two Grand Oaks campuses, a ninth-grade campus in the Caney Creek High School feeder, a new Conroe-area high school, junior high and intermediate school.
The Woodlands High School feeder elementary project
- Construction company: Marshall Construction
- Guaranteed maximum price: $45 million
- Construction begins: March 1
- Potential completion date: May 30, 2025
- Construction company: Marshall Construction
- Guaranteed maximum price: $44.8 million
- Construction begins: March 1
- Potential completion date: May 30, 2025
Other projects
Major renovations are scheduled for Creighton Elementary, San Jacinto Elementary, Oak Ridge High School's ninth-grade campus, Knox Junior High and The Woodlands High School. Additions are planned for Hailey Elementary, Ford Elementary and McCullough Junior High.
- Tellepsen Builders was selected for the Hailey Elementary, Ford Elementary and McCullough Junior High School projects.
- Pogue Construction Co. was selected for The Woodlands High School addition and the Oak Ridge High School Master Plan Phase II projects.
- Satterfield & Pontikes Construction was selected for the Washington High School addition and Knox Junior High School renovation projects.