Timeline: construction begins spring 2024
Cost: $6.3 million (including Phase 2)
Funding source: city of League City
The second phase of this project includes improvements to Butler Road from Cross Springs Lane south to Ervin Street. Additionally, 1,800 linear feet of an 8-inch waterline will be installed from Tempe Street to Sedona Drive.
Timeline: construction begins after October 2024
Cost: $6.3 million (including Phase 1)
Funding source: city of League City