In February, crews completed preparation of the center medians for future landscaping throughout the project limits on SH 26 between John McCain Road and Brown Trail in Colleyville. Over the coming weeks, construction activity will include the continuing installation of sidewalks, retaining walls, railings and permanent traffic signals. Crews will also soon begin irrigation installation. The state project is expected to wrap up this spring. Following this, the city will begin beautification efforts on the sidewalks and medians.

Timeline: November 2016-spring 2020

Cost: $38.2 million

Funding source: Texas Department of Transportation