Here are 10 transportation projects that are underway or coming soon to Frisco. This list is not comprehensive.

Upcoming

1. Hillcrest Road improvements


Project: Hillcrest Road is expected to see improvements from SH 121 to Main Street in the coming years.

Update: The project is in the design phase.
  • Timeline: mid 2027-end 2028
  • Cost: $12 million
  • Funding source: city of Frisco
2. Lebanon Road widening


Project: Lebanon Road will be widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive.

Update: The project is in the design phase and expected to start construction later this year.
  • Timeline: late 2025-mid 2027
  • Cost: $26.5 million
  • Funding sources: city of Frisco, external funding
3. Legacy Drive and Stonebrook Parkway widening

Project: The project spans Legacy Drive from Lebanon Road to Stonebrook Parkway and Stonebook Parkway from Legacy Drive to 4th Army Drive. The project will widen and reconstruct the roadway.

Update: The project is in the design phase.
  • Timeline: mid 2026-December 2027
  • Cost: $15 million
  • Funding source: city of Frisco
4. Legacy Drive improvements


Project: The project spans Legacy Drive from Main Street to Panther Creek Parkway. Details on the project are not yet available.

Update: The project is in the planning phase.
  • Timeline: early 2027-mid 2028
  • Cost: $13.6 million
  • Funding source: city of Frisco
Ongoing

5. Mahard Parkway construction


Project: The project will construct a six-lane roadway from PGA Parkway to US 380.


Update: The project is under construction and is expected to be completed next year.
  • Timeline: Q4 2024-Q4 2026
  • Cost: $11.03 million
  • Funding source: city of Frisco
6. Panther Creek Parkway construction

Project: The project will construct a six-lane divided roadway from Dallas North Tollway to Preston Road.

Update: The road is under construction and expected to be completed later this year, according to the city’s capital improvement website.
  • Timeline: early 2024-December 2025
  • Cost: $56.4 million
  • Funding sources: city of Frisco, Collin County
7. Fields Parkway traffic signal installation

Project: A new traffic signal is being installed at the Fields Parkway and Dallas Parkway intersection. The traffic light is adjacent to the new Universal Kids Resort theme park.


Update: The project is under construction.
  • Timeline: mid 2025-mid 2026
  • Cost: $350,000
  • Funding source: city of Frisco
8. Hillcrest Road construction

Project: Hillcrest Road is being constructed to a four-lane divided roadway from Panther Creek Parkway to PGA Parkway.

Update: The project is under construction and is expected to be completed later this year.
  • Timeline: early 2024-December 2025
  • Cost: $5.99 million
  • Funding source: city of Frisco
9. Main Street improvements

Project: The project includes Main Street from DNSF railroad to North County Road and Fourth Street from Main Street to Elm Street. The construction includes modified cross sections, increased sidewalk widths and improved intersections. It will also construct a pedestrian plaza. The overall project also includes a parking garage, which will be completed in May 2026.


Update: This is phase two and three of the Main Street construction project through the rail district. Main Street construction started in 2024 and the entire project is expected to wrap in May 2026.
  • Timeline: early 2024-December 2025
  • Cost: $20.54 million
  • Funding source: city of Frisco
10. PGA Parkway construction

Project: The project will construct a six-lane divided roadway from Preston Road to Coit Road along PGA Parkway.

Update: The project is under construction and should be completed next year.
  • Timeline: end 2024-mid 2026
  • Cost: $31.1 million
  • Funding sources: city of Frisco, external funding