Upcoming projects
1. Widen roadway on Teel Parkway Project: Teel Parkway from Stafford Middle School to Olive Branch Drive will be widened from two to four lanes.
Update: The project is in the design phase.
- Timeline: Q3 2025-Q4 2026
- Cost: $12 million
- Funding sources: city of Frisco
Project: New roundabouts are being designed for Frisco Street. They will go on Technology Drive, Sports Village Road, All Stars Avenue and Research Road.
Update: The project is in the design phase, which should be completed in Q3 2026.
- Timeline: Q3 2026-Q1 2028
- Cost: $12 million
- Funding sources: city of Frisco
3. New traffic signal on Custer Trail
Project: A new traffic signal is being installed on Custer Trail at Bighorn Trail.
Update: Design on the signal was finished in Q3 2024 and it is currently under construction.
- Timeline: Q3 2024-Q2 2025
- Cost: $350,000
- Funding source: external
Project: A new traffic signal will be installed on Stonerbook Drive at Witt Road.
Update: The project is currently under construction and design was completed in 2024.
- Timeline: Q4 2024-Q2 2025
- Cost: $250,000
- Funding source: city of Frisco
Project: Six new lanes are being constructed on Mahard Parkway between US 380 and PGA Parkway.
Update: Construction is ongoing and expected to finish in 2026.
- Timeline: Q4 2024-Q4 2026
- Cost: $11 million
- Funding source: city of Frisco
Project: A new lane will be constructed on the north and southbound frontage roads on Dallas Parkway from Lebanon Road to Eldorado Parkway.
Update: The new lane is currently under construction.
- Timeline: Q4 2023- Q4 2025
- Cost: $10.3 million
- Funding source: city of Frisco
Project: A new four-lane roadway is being constructed on Hillcrest Road. The new roadway will run from Panther Creek Parkway to PGA Parkway.
Update: Design on the project wrapped up in 2024 and construction is underway.
- Timeline: Q1 2024-Q3 2025
- Cost: $5.9 million
- Funding source: city of Frisco
Project: A pedestrian plaza will be constructed, intersections will be improved and sidewalks will be widened.
Update: Design was completed in 2024 and construction is underway.
- Timeline: Q1 2024-Q4 2025
- Cost: $20.5 million
- Funding source: city of Frisco
Project: A new six-lane roadway is being constructed on Panther Creek Parkway from Dallas North Tollway to Preston Road.
Update: The new roadway is under construction.
- Timeline: Q1 2024-Q4 2025
- Cost: $56.4 million
- Funding source: city of Frisco, external
Project: A new six-lane roadway is being constructed on PGA Parkway from Preston Road to Coit Road.
Update: This project is under construction and is set to include a new water line.
- Timeline: Q1 2024-Q2 2026
- Cost: $31.1 million
- Funding source: city of Frisco, external