Check out these 10 transportation projects in Frisco.

Upcoming projects

1. Widen roadway on Teel Parkway
Project: Teel Parkway from Stafford Middle School to Olive Branch Drive will be widened from two to four lanes.

Update: The project is in the design phase.
  • Timeline: Q3 2025-Q4 2026
  • Cost: $12 million
  • Funding sources: city of Frisco
2. New roundabouts on Frisco Street

Project: New roundabouts are being designed for Frisco Street. They will go on Technology Drive, Sports Village Road, All Stars Avenue and Research Road.


Update: The project is in the design phase, which should be completed in Q3 2026.
  • Timeline: Q3 2026-Q1 2028
  • Cost: $12 million
  • Funding sources: city of Frisco
Ongoing projects

3. New traffic signal on Custer Trail

Project:
A new traffic signal is being installed on Custer Trail at Bighorn Trail.

Update: Design on the signal was finished in Q3 2024 and it is currently under construction.
  • Timeline: Q3 2024-Q2 2025
  • Cost: $350,000
  • Funding source: external
4. New traffic signal on Stonebrook Drive


Project:
A new traffic signal will be installed on Stonerbook Drive at Witt Road.

Update: The project is currently under construction and design was completed in 2024.
  • Timeline: Q4 2024-Q2 2025
  • Cost: $250,000
  • Funding source: city of Frisco
5. New lanes on Mahard Parkway

Project:
Six new lanes are being constructed on Mahard Parkway between US 380 and PGA Parkway.

Update: Construction is ongoing and expected to finish in 2026.
  • Timeline: Q4 2024-Q4 2026
  • Cost: $11 million
  • Funding source: city of Frisco
6. New frontage road lane on Dallas Parkway


Project:
A new lane will be constructed on the north and southbound frontage roads on Dallas Parkway from Lebanon Road to Eldorado Parkway.

Update: The new lane is currently under construction.
  • Timeline: Q4 2023- Q4 2025
  • Cost: $10.3 million
  • Funding source: city of Frisco
7. New divided roadway on Hillcrest Road

Project:
A new four-lane roadway is being constructed on Hillcrest Road. The new roadway will run from Panther Creek Parkway to PGA Parkway.

Update: Design on the project wrapped up in 2024 and construction is underway.
  • Timeline: Q1 2024-Q3 2025
  • Cost: $5.9 million
  • Funding source: city of Frisco
8. Main and 4th street improvements


Project:
A pedestrian plaza will be constructed, intersections will be improved and sidewalks will be widened.

Update: Design was completed in 2024 and construction is underway.
  • Timeline: Q1 2024-Q4 2025
  • Cost: $20.5 million
  • Funding source: city of Frisco
9. New divided roadway on Panther Creek Parkway

Project:
A new six-lane roadway is being constructed on Panther Creek Parkway from Dallas North Tollway to Preston Road.

Update: The new roadway is under construction.
  • Timeline: Q1 2024-Q4 2025
  • Cost: $56.4 million
  • Funding source: city of Frisco, external
10. New divided roadway on PGA Parkway


Project:
A new six-lane roadway is being constructed on PGA Parkway from Preston Road to Coit Road.

Update: This project is under construction and is set to include a new water line.
  • Timeline: Q1 2024-Q2 2026
  • Cost: $31.1 million
  • Funding source: city of Frisco, external