Construction is halfway done to add a six-lane divided roadway and a 24-inch water line on Rockhill Parkway from west of Legacy Drive to Mahard Parkway, according to the city’s monthly engineering report. Work could wrap up as late as September.
Timeline: January-September (construction)
Cost: $12.3 million
Funding source: city of Frisco