Rockhill Parkway construction in Frisco halfway completed

The Rockhill Parkway project will construct a six-lane divided roadway and add a 24-inch water line. (Courtesy Adobe Stock)
The Rockhill Parkway project will construct a six-lane divided roadway and add a 24-inch water line. (Courtesy Adobe Stock)

The Rockhill Parkway project will construct a six-lane divided roadway and add a 24-inch water line. (Courtesy Adobe Stock)

Construction is halfway done to add a six-lane divided roadway and a 24-inch water line on Rockhill Parkway from west of Legacy Drive to Mahard Parkway, according to the city’s monthly engineering report. Work could wrap up as late as September.

Timeline: January-September (construction)


Cost: $12.3 million

Funding source: city of Frisco