Curious about the future of development in Frisco? There are multiple multi-million dollar projects slated to begin in 2023 throughout the city. The following projects’ costs add to nearly $337 million. See some of the largest upcoming projects in Frisco below. The following projects have been filed through the Texas Department of Licensing and Regulation. The following information may be subject to change.

FCS Office Interiors: 10401 John W Elliott Drive, Ste. 100, Frisco

Type of work: New construction

Timeline: June 1, 2023-Oct. 31, 2023

Estimated cost: $2 million


Frisco Flyers Addition: Northwest corner of All Stars Ave. and John Elliott Drive, Frisco

Type of work: New construction

Timeline: Jan. 1, 2023-June 30, 2023

Estimated cost: $4.5 million


Heritage Business Park: 11691 Independence Parkway Building 100, Frisco

Type of work: New construction

Timeline: Jan. 1, 2022-Dec. 1, 2023

Estimated cost: $1 million


The following project is part of the Fields development project in Frisco and has yet to determine an address. The project is a 4 story, 257-unit multifamily project with leasing and fitness amenities.

North Fields Block A, Lot 1: TBD

Type of work: New construction

Timeline: March 20, 2023-Dec. 31, 2024


Estimated cost: $73 million

The Star: 17 Cowboys Way, Frisco

Type of work: Renovation/alteration

Timeline: Dec. 1, 2022-Dec. 31, 2023


Estimated cost: $2.8 million

Jefferson Railhead: Located off of the Dallas North Tollway, bordered by Eldorado Parkway on the north and Main Street

Type of work: New construction

Timeline: Jan. 1, 2023-Jan. 1, 2025

Estimated cost: $99 million

Frisco Police Department: 7200 Stonebrook Pkwy, Frisco

Type of work: New construction

Timeline: Dec. 12, 2022-Nov. 17, 2023

Estimated cost: Approximately $6.8 million

Hall Park: 3010 Gaylord Parkway, Frisco

Type of work: New construction

Timeline: Dec. 1, 2022-Dec. 1, 2023

Estimated cost: $10 million

The next three projects are part of the Project X development for urban living units. The projects have yet to determine an address.

Project X - Urban Living Units: TBD

Type of work: New construction

Timeline: Jan. 30, 2023-May 29, 2026

Estimated cost: Approximately $7 million

Project X - East: TBD

Type of work: New construction

Timeline: Jan. 30, 2023-May 29, 2026

Estimated cost: Approximately $54.8 million

Project X - West: TBD

Type of work: New construction

Timeline: Jan. 30, 2023-May 29, 2026

Estimated cost: Approximately $76 million