SBK-2015-08-101. FM 150 center turn lane

Hays County and the Texas Department of Transportation will add a center turn lane to the 3.8-mile portion of FM 150 from Lox to Hwy. 21. Construction crews were waiting for utilities to be relocated throughout the project area before starting work on the road as of Aug. 6.

Timeline: Late 2015-late 2016 Cost: $4.68 million Funding sources: Hays County

2. Hwy. 123 & Wonder World overpass

TxDOT is constructing an overpass on Hwy. 123 in San Marcos that will span Wonder World Drive. A signal will be built at the intersection as well as a bridge with two lanes in each direction and access roads with two lanes in each direction.

Timeline: March 2015-mid-2017 Cost: $11.6 million Funding sources: TxDOT

3. Hunter Road widening

Project Engineer Richard Reynosa said work is nearly complete on the widening project, which spans from near Bishop Street to Wonder World Drive in San Marcos. Final paving of the project was scheduled for mid-August.

Timeline: March 2014-August 2015 Cost: $6.9 million Funding sources: TxDOT, city of San Marcos

4.Goforth Road widening

This project, spanning I-35 to Bunton Creek Road in Kyle, will widen the two-lane road to three lanes in some areas and four lanes in others. Right of way acquisition is nearly complete, and construction could start by early 2016.

Timeline: TBA Cost: $9.04 million Funding sources: city of Kyle