Austin Stone Community Church: 6505 Airport Blvd., Ste. 110, Austin
Type of work: renovation/alteration
Estimated cost: $2.3 million
Timeline: Aug. 1-Jan. 31
Scope of work: interior remodel
5th Street Creative Office: 5200 E. Fifth St., Austin
Type of work: new construction
Estimated cost: $14.17 million
Timeline: Oct. 1, 2022-Oct. 31, 2023
Scope of work: 27,400-square-foot four-story office building shell; site work not included
816 Congress - Spec Suites: 816 Congress Ave., Austin.
Type of work: renovation/alteration
Estimated cost: $4.97 million
Timeline: Aug. 31-Dec. 29
Scope of work: renovations of suites 500, 700, 710, 1120, 1200 and 1800
Pediatric Associates of Austin: 1600 W. 38th St., Ste. 100 & 150, Austin
Type of work: renovation/alteration
Estimated cost: $2.5 million
Timeline: Aug. 1-Dec. 31
Scope of work: three existing suites to be converted to two suites; construction scope to include a full renovation of interior walls, doors, ceilings, lighting and plumbing
Austin-Bergstrom International Airport existing terminal centralized baggage handling system upgrades: 3600 Presidential Blvd., Austin.
Type of work: Additions to existing building
Estimated cost: $42 million
Timeline: Oct. 1, 2022-Dec. 31, 2024
Scope of work: Expansion of the checked baggage system, security screening checkpoint and additional tenant offices and lounges; removal and relocation of select utility lines above head to allow new baggage system equipment installation at the exterior apron
Faulk Building and History Center renovation: 800 Guadalupe St., Austin
Type of work: renovation/alteration
Estimated cost: $12.7 million
Timeline: June 15, 2022-Oct. 9, 2023
Scope of work: renovation of levels two and three for archive storage use; finish renovation of office area on level four; renovation and modification of restrooms on all levels to comply with accessibility requirements
2908 San Gabriel building repair: 2908 San Gabriel St., Austin
Type of work: renovation/alteration
Estimated cost: $100,000
Timeline: July 1-Dec. 1
Scope of work: repairs to the existing exterior wall and related interior repairs of a building hit by a car
The Moody Center locker rooms: 2001 Robert Dedman Drive, Austin
Type of work: new construction
Estimated cost: $3.5 million
Timeline: Nov. 11, 2021-Aug. 1, 2022
Scope of work: new interior finish-out for the men’s and women’s University of Texas basketball programs inside The Moody Center, a multipurpose sports and entertainment arena for basketball games and other events
Helipad Relocation at Ascension Seton Medical Center: 1201 W. 38th St., Austin
Type of work: additions to existing building
Estimated cost: $4.5 million
Timeline: Oct. 15, 2022-May 31, 2023
Scope of work: adding a new helipad to the existing floor, extending the existing fire stair up to the roof and adding a new vestibule, adding a new elevator from the ground floor to the existing roof line
High-rise mixed-use office tower: 208 E. Fourth St., Austin
Type of work: new construction
Estimated cost: $275 million
Timeline: Nov. 1, 2022-Nov. 1, 2025
Scope of work: ground- and second-level lobby and retail with levels 3-19 structured parking; levels 20 and 21 are the sky lobby and office amenities; levels 22-44 are office levels and amenities; level 45 is an amenity deck; and level 46 is a rooftop penthouse