State and federal funding for the T.C. Jester Stormwater Detention Basin project was secured Sept. 25, according to a Sept. 26 news release.
The details
The T.C. Jester Stormwater Detention Basin is a project managed by the Harris County Flood Control District in the Cypress Creek watershed designed to reduce flooding in the area, benefiting both homes and businesses, according to the release.
The project will be located north of Cypress Creek and south of Cypresswood Drive in Spring, with efforts on both the west and east sides of T.C. Jester Boulevard, according to the release.
- U.S. Rep. Dan Crenshaw, R-Houston, gave $9.95 million in funding for the project in fiscal year 2022-23 through the Federal Emergency Management Agency Pre-Disaster Mitigation Program.
- State Rep. Sam Harless, R-Spring, gave $12 million in funding for the project through direct state allocation.
- A potential $27.7 million will be given through the Community Development Block Grant Mitigation Funds.