Several transportation projects were recently completed in the New Braunfels area and two others are approaching the finish line, opening more roadway use to drivers.

Upcoming projects

Goodwin Lane/Conrads Lane

Project: Full reconstruction of the two connecting roads will include sidewalks, curbs utilities, drainage and a new turning lane throughout Conrads Lane.

Update: The projects are progressing through their respective design and predesign phases, laying the groundwork for future construction and improvements, said Scott McClelland, assistant director of transportation and capital improvements for the city of New Braunfels.
  • Timeline: Beginning late 2024
  • Cost: $10.7 million
  • Funding source: 2019 Bond
McQueeney Road


Project: Spot repairs of the roadway base and a complete mill and overlay of the road will take place later this year, from I-35 to County Line Road, said Brenadette Faust, capital projects manager for the city of New Braunfels.

Update: New Braunfels Utilities completed its McQueeney Road 24-inch water line project in 2023.
  • Timeline: Beginning fall 2024
  • Cost: $2.16 million
  • Funding source: 2023 Bond
South Union Avenue improvements

Project:
There will be roadway rehabilitation from Common Street to Lincoln Street, which will include pedestrian and intersection improvements.

Update: The project design is nearing completion and construction is to begin soon.
  • Timeline: Bidding later this summer, construction fall 2024–TBD
  • Cost: $2.5 million
  • Funding source: 2023 bond citywide streets program
Ongoing Projects


Klein Road expansion

Project: Crews continue to work on the expansion of Klein Road from Walnut Avenue to FM 725, incorporating increased lane capacity and pedestrian and drainage improvements.

Update: The project is ongoing as construction continues and on track to be complete. Lane closures and diversions to one lane will continue.
  • Timeline: May 2023-fall 2024
  • Cost: $17.5 million
  • Funding source: 2019 Bond
I-35 turnaround at FM 725

Project:
Reconstruction work continues on the I-35 southbound to northbound turnaround at FM 725. The northbound to southbound side was completed in the winter, said Tanya Brown, a spokesperson for the Texas Department of Transportation.


Update: Construction crews have begun paving the roadway for the turnaround and are working to install a raised curb, Brown said. The original completion date was expected to be September 2023. Brown said the timeline for completing the project was pushed back due to material acquisition delays as well as a change in contractors.
  • Timeline: January 2022-August 2024
  • Cost: $5.4 million
  • Funding source: State and federal