Check out five upcoming and ongoing transportation projects around Dallas-Fort Worth.
This list is not comprehensive.
Upcoming projects
Dallas Parkway repairs
Project: Construction crews will repair multiple sections of northbound Dallas Parkway in Prosper starting early next year.
Update: Town officials expect work to start in late January or early February of 2027, and the construction has a 120-day timeline. Officials are still deciding whether to spread out the closures along Dallas Parkway or close everything down at once.
Collins Boulevard overpass improvements
Project: Richardson’s Collins Boulevard overpass project includes modifications to existing bicycle and traffic lanes. Further work includes signal and sidewalk improvements.
Update: City officials are preparing to award a contract for the project, which is expected to begin next year.
Ongoing projects
Medical Center Drive improvements
Project: Crews are reconstructing and widening Medical Center Drive in McKinney between Frisco Road and Spur 399. When finished, the road will be a continuous four-lane divided roadway.
Update: Construction is about 86% complete.
Robson Ranch Road widening
Project: New lanes are going in on Denton County’s Robson Ranch Road from I-35 to Sagehawk Drive and at the intersection with Gibbs Road and Ed Robison Boulevard.
Update: Crews are preparing the ground to start paving the new roadway, and certain lanes are closed to accommodate the work.
Custer Road water main replacement
Project: The North Texas Municipal Water District, or NTMWD, is replacing an aging 30-inch pipeline along Custer Road in southern Plano and into Richardson.
Update: Plano’s Director of Engineering Mark Simon said 99% of the pipeline has been installed and the project is estimated to be completed by the end of November. Repavement is expected to be completed in January 2027.