Concrete panel replacement along Virginia Parkway is nearly complete for now, but more work is expected next summer. Here are six updates on current or planned transportation projects in McKinney.
This list is not comprehensive. Residents can learn more about additional projects through McKinney's Capital Improvements Program website, which tracks road projects in the city.
Upcoming
Spur 399 utility relocations
Project: The City of McKinney’s water and wastewater utilities will be relocated in advance of the Texas Department of Transportation’s upcoming reconstruction project along Spur 399.
Update: Design is complete. Easement acquisition is underway and construction is expected to begin in early 2027 with a six- to eight-month duration.
Silverado Trail lane expansion
Project: Westbound lanes of Silverado Trail will be constructed between Kenley Drive and Burnett Drive, including a bridge over Rowlett Creek. The project includes the relocation of an existing North Texas Municipal Water District sanitary sewer line.
Update: Design is 97% complete. The project is expected to bid in early 2027.
SH 5 Utility Relocations Phase 2
Project: City utilities, including water and wastewater lines, will be relocated in advance of the Texas Department of Transportation’s reconstruction project along SH 5.
Update: Design is complete. The project is expected to bid in early 2027.
Ongoing
SH 5 Utility Relocations Phase 1
Project: The City of McKinney’s water and wastewater utilities will be relocated in advance of TxDOT’s upcoming reconstruction project along SH 5.
Update: Construction is about 87% complete. Various locations along SH 5 between Elm Street and US 380 will experience localized lane closures and detours to complete remaining construction.
Medical Center Drive improvements
Project: Crews are reconstructing and widening Medical Center Drive between Frisco Road and Spur 399. When finished, the road will be a continuous four-lane divided roadway.
Update: Construction is about 86% complete.
6. Eldorado Parkway and Virginia Parkway rehabilitation
Project: Reconstruction of failing concrete panels and broken curbs will occur along Eldorado Parkway between Ridge Road and US 75, and Virginia Parkway between Stonebridge Drive and US 75.
Update: Work on Eldorado Parkway is complete. Work continues on Virginia Parkway between Lake Forest Drive and Hardin Boulevard. Any remaining work on Virginia Parkway between Hardin Boulevard and US 75 will be completed in summer 2027 after the project is rebid.