Pleasant Run Road
The road is being reconstructed as a two-lane, 31-foot-wide asphalt street with concrete curbs and gutters. In early September the contractor placed the driveways from Church Street to Central Drive. They also placed the other half of Regina Court. Throughout the month the contractor will be placing more driveways and start on the sidewalks and trail. Also, asphalt should be placed from Church to Mission Lane. The road is closed from Mission to Church.
Timeline: January-November
Cost: $2 million
Funding sources: city of Colleyville, North Central Texas Council of Governments Trail Grant Fund
FM 2499
In August crews began concrete paving on the FM 2499 main lanes from SH 121 to Grapevine Mills Boulevard in Grapevine. Drainage and wall work continues on the new, lowered FM 2499 main lanes from Grapevine Mills Boulevard to the north. Crews are back to work on the new southbound FM 2499 bridge over Denton Creek, which has been flooded since June.
Timeline: August 2013-January 2017
Cost: $93 million
Funding sources: Texas Department of Transportation, federal grant funds
SH 121/SH 360
In July and August construction workers set beams on two bridges for the new SH 121 on-ramp. Crews are working on placing concrete for the decks of these bridges in September. Workers continue concrete paving on the ramps to SH 121/SH 360. When the project is complete, there will be two new ramps connecting southbound William D. Tate Avenue in Grapevine to SH 121 and
SH 360.
Timeline: February 2015-January 2017
Cost: $17 million
Funding sources: TxDOT