Gosling Road Segment 3 widening
Construction is underway on a project to widen Gosling Road from two to four lanes with a raised median between West Rayford Road and Creekside Forest Drive in the Creekside Park area.
Timeline: second quarter 2021-fourth quarter 2022
Cost: $7.4 million
Funding source: Harris County Precinct 3
Gosling Road bridge widening
Work on a new bridge is underway over Spring Creek as part of a 14- to 15-month project to widen Gosling Road to four lanes between Creekside Forest Drive and Gatewood Reserve Lane. The project is a joint effort between Montgomery County Precinct 3 and Harris County Precinct 3. Contractor NBG Constructors completed the concrete pavement as of an Oct. 17 update from Montgomery County. The next work slated includes the approach slab, south side paving, bridge rails, slope paving, sod and seed, according to Montgomery County officials. The project will create two 12-foot lanes in each direction as well as the two additional lanes for a 1,817-foot bridge over Spring Creek. The project is the last budgeted project from the 2015 road bond.
Timeline: December 2021-early 2023
Cost: $8.2 million
Funding sources: Montgomery County Precinct 3, Harris County Precinct 3
Sawdust Road turn lane
Contractor Teamwork was almost finished with building a left-turn lane from westbound Sawdust Road onto southbound Melda Road in mid-October. As of Oct. 17, asphalt and curb work was completed, and striping was completed in late October.
Timeline: completed in October
Cost: $49,608
Funding source: Montgomery County Precinct 3
Kuykendahl Road turn lane
The contracting company Teamwork will add a right-turn lane from northbound Kuykendahl Road onto eastbound Research Forest Drive as well as extend the left-turn lane from northbound Kuykendahl Road onto westbound Research Forest Drive.
Timeline: TBD
Cost: $212,224
Funding source: Montgomery County Precinct 3