Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Park 8Ninety: 631 Hwy. 90A, Ste. 100, Missouri City

Type of work: new construction

Timeline: April 4-Oct. 4

Estimated cost: $559,321


2. Ultra Lash: 16230 City Walk, Sugar Land

Type of work: renovation/alteration

Timeline: May 18-Nov. 18

Estimated cost: $250,000


3. Tillys: 16535 Southwest Freeway, Ste. 305, Sugar Land

Type of work: renovation/alteration

Timeline: April 11-July 20

Estimated cost: $250,000


4. Grand Parkway Medical Office Building: 6424 E. Riverpark Drive, Sugar Land

Type of work: new construction

Timeline: May 2, 2022- May 2, 2023

Estimated cost: $8.3 million


5. Baby's & Kid's 1st: 2268 Lone Star Drive, Sugar Land

Type of work: renovation/alteration

Timeline: May 5-Aug. 6

Estimated cost: $79,500