Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

1. Dickey's Barbecue Pit: 15823 Southwest Freeway, Ste. B22, Sugar Land

Type of work: renovation/alteration

Timeline: March 1-June 1

Estimated cost: $350,000


2. Amazon: 16535 Southwest Freeway, Ste. 45, Sugar Land

Type of work: renovation/alteration

Timeline: May 23-Sept. 7

Estimated cost: $640,000


3. Rouxpour: 2298 Texas Drive, Sugar Land

Type of work: renovation/alteration

Timeline: March 21-Aug. 26

Estimated cost: $800,000


4. Thomas Plaza: ​​2710 FM 1092, Missouri City

Type of work: new construction

Timeline: April 4-Aug. 8

Estimated cost: $1.05 million


5. Citypark Logistics Center: 12613 Citypark Drive, Ste.100, Missouri City

Type of work: renovation/alteration

Timeline: March 1-Sept. 30

Estimated cost: $1.6 million