Read about some of the latest updates on transportation projects in the Katy-Fulshear area. This list is not comprehensive.
Porter Road widening
Project: The project will widen Porter Road from two lanes to four lanes between Morton Ranch Road and Clay Road. The project will also add underground storm sewers.
Update: Construction is ongoing and on track to be completed by April 2027.
Timeline: June 2026-April 2027
Cost: $4.5 million (construction)
Funding source: Harris County Precinct 4
Project: The project will add a traffic signal at the intersection of Katy Hockley Cut Off Road and Heritage Drive.