See the latest updates on four transportation projects in the Lake Houston area. This list is not comprehensive.

Upcoming projects

West Lake Houston Parkway sidewalk
  • Project: Sidewalks will be constructed along West Lake Houston Parkway from Summer Lake Ranch Drive to Lakewood Pines Boulevard.
  • Update: This project is in the design phase.
  • Timeline: third quarter 2024-fourth quarter 2024
  • Cost: TBD
  • Funding source: Harris County Precinct 3
West Lake Houston Parkway, Firesign Drive traffic signal
  • Project: The traffic signal will be rebuilt at the intersection of West Lake Houston Parkway and Firesign Drive.
  • Update: This project is in the design phase.
  • Timeline: first quarter 2025-second quarter 2025
  • Cost: TBD
  • Funding source: Harris County Precinct 3
West Lake Houston Parkway, Kings River Drive/Kings Lake Estates Boulevard traffic signal
  • Project: The traffic signal will be rebuilt at the intersection of West Lake Houston Parkway and Kings River Drive/Kings Lake Estates Boulevard.
  • Update: This project is in the design phase.
  • Timeline: first quarter 2025-second quarter 2025
  • Cost: TBD
  • Funding source: Harris County Precinct 3
Ongoing projects

Townsen Park-N-Ride Multimodal Connector
  • Project: An 8-foot-wide concrete hike and bike trail will be constructed to connect the Townsen Park-and-Ride to the I-69 Historical Pedestrian Bridge Metro Park-and-Ride.
  • Update: This project is under construction.
  • Timeline: March 2024-third quarter 2025
  • Cost: $1.5 million
  • Funding sources: Harris County Precinct 3, Texas Department of Transportation