As a part of the I-45 widening project between FM 518 and FM 517, the Texas Department of Transportation will reconstruct the intersection of I-45 and League City Parkway. The work will happen in four phases.

First, the eastbound side of League City Parkway and outside lanes of the I-45 north- and southbound frontage roads will be reconstructed. During Phase 2, the north and south U-turns and the inside lanes of the north- and southbound frontage roads will be built.

The intersection will then be closed for a weekend to reconstruct the westbound League City Parkway pavement in the middle of the intersections at both frontage roads. During Phase 4, the westbound side of League City Parkway will be reconstructed.

Timeline: fall 2019-spring 2020

Cost: $850,000


Funding source: Texas Department of Transportation