To solve drainage issues along Clear Creek, experts working on the Lower Clear Creek and Dickinson Bayou Watershed Study have proposed several potential flood mitigation projects, including building miles of underground tunnels.
At a Nov. 4 meeting to update residents on the progress of the study, consulting firm Freese and Nichols, which is working with League City officials on the study, showed a map detailing 27 potential projects that could help address Clear Creek’s flooding during heavy storms.
Of the 27 projects, eight are storage projects, such as detention areas, mainly located upstream. The remaining 19 are conveyance projects, or bypass channels, including underground tunnels, which are meant to move more water quickly to Clear Lake and Galveston Bay.
"This is essentially a bypass channel. It’s just a bypass channel that’s underground,” said Brian Gettinger, a project manager with Freese and Nichols. “I can assure you that tunnels are quite doable here.”