Curious as to what new businesses and renovations are underway or coming to the Bay Area? The following projects have been filed in the last month through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Tesla: 400 Gulf Freeway S., League City
Type of work: renovation/alteration
Timeline: Nov. 15, 2022-March 15, 2023
Estimated cost: $3 million
2. Five Guys Burger & Fries: 1615 FM 646, League City
Type of work: renovation/alteration
Timeline: Dec. 5-Dec. 23
Estimated cost: $300,000
3. Tiff’s Treats: 201 S. FM 270, League City
Type of work: renovation/alteration
Timeline: July 1-Oct. 1
Estimated cost: $400,000
4. Daiquiri Retreat: 1504 W. League City Pkwy., Ste. 200, League City
Type of work: renovation/alteration
Timeline: Oct. 17-Dec. 16
Estimated cost: $300,000
5. Magnolia Living Senior Apartments Clubhouse: Hobbs Road., League City
Type of work: new construction
Timeline: Sept. 19, 2022-Jan. 28, 2024
Estimated cost: $3 million
6. In-N-Out Burger: 122 El Dorado Blvd., Webster
Type of work: new construction
Timeline: Jan. 3, 2023-Aug. 15, 2023
Estimated cost: $1.5 million
7. Black Line Coffee: 203 E. Nasa Road, Webster
Type of work: renovation/alteration
Timeline: Sept. 1-Dec. 1
Estimated cost: $75,000
8. Twin Liquors: 148 El Dorado Blvd., Ste. 120, Webster
Type of work: new construction
Timeline: Nov. 15, 2022-Jan. 30, 2023
Estimated cost: $240,000
9. Dr. Das: 17330 Hwy. 3, Webster
Type of work: renovation/alteration
Timeline: Nov. 1, 2022-June 30, 2023
Estimated cost: $400,000
10. Lucchese Bootmaker: 700 Baybrook Mall Drive, Friendswood
Type of work: renovation/alteration
Timeline: Oct. 17, 2022-Feb. 24, 2023
Estimated cost: $125,000