1 Custer Road bond project
Work has begun on the Custer Road improvement project, one of the last 2015 bond program projects awaiting completion. Various lane closures are expected throughout this year on Custer between Arapaho Road and Campbell Road as the street is transformed from its current lane design to a new configuration with one northbound lane, one southbound lane, a continuous left-turn lane in the center, a dedicated at-grade bike lane in each direction and 5-foot sidewalks on each side. In addition, a pedestrian crossing at Northrich Elementary School will be enhanced with a raised median island and rectangular rapid flashing beacons.
Timeline: March 2022-early 2023
Cost: $8,462,578
Funding source: city of Richardson 2015 bond
2 Plano Road concrete rehabilitation
Various lanes of northbound and southbound Plano Road between Buckingham Road and the President George Bush Turnpike may be closed to traffic in different locations from 9 a.m.-3:30 p.m. daily while concrete rehabilitation—joint and crack sealing—takes place. While the work is scheduled to be complete by mid-April, some of the lanes, specifically between Belt Line Road and 505 Plano Road, in front of Richardson Square Mall, may still experience closures through late May due to fiber-optic work.
Timeline: mid-February-mid-April/late May
Cost: $225,000
Funding source: city of Richardson
3 Fiber-optic work on Renner/North Star roads
The right-turn lanes of eastbound and westbound Renner Road onto southbound and northbound North Star Road may be closed to traffic from 9 a.m.-3:30 p.m. daily due to fiber-optic work. The work is expected to be complete by early May.
Timeline: mid-February-early May
Cost: not available, privately funded
Funding source: franchise utility company Spectrum
4 Fiber-optic work along US 75 frontage road
The right lane of the southbound US 75 frontage road between Renner Road and Palisades Creek Drive may be closed to traffic from 9 a.m.-3:30 p.m. daily for fiber-optic work. The work is expected to be complete in late May.
Timeline: late February-late May
Cost: not available, privately funded
Funding source: franchise utility company Spectrum