Richardson city officials: Plano Road pavement repair should wrap up this month

0

Plano Road repairs that began in January should be complete by the end of December, Richardson city officials say.

The $1 million project repaired broken pavement along a roughly 5-mile stretch of Plano Road between Buckingham Road and President George Bush Turnpike. After repairs between Renner and Belt Line roads wrapped up in November, construction crews moved south of Belt Line to Buckingham.

In January crews will begin restriping the road, weather permitting.

Share this story
COMMENT

Leave A Reply

Olivia Lueckemeyer
Olivia Lueckemeyer graduated in 2013 from Loyola University New Orleans with a degree in journalism. She joined Community Impact Newspaper in October 2016 as reporter for the Southwest Austin edition before her promotion to editor in March 2017. In July 2018 she returned home to the Dallas area and became editor of the Richardson edition.