Spring Creek and Independence Parkways
Work continues to reconstruct the Spring Creek Parkway and Independence Parkway intersection. The project includes creating double left turn lanes and a right turn lane in all four traffic directions.
The original plan for the intersection was to create an overpass on Spring Creek Parkway, but because the City Council decided not to create that overpass, the area will now be constructed into a normal intersection.
This project is being done in two phases. The first phase to reconstruct the Spring Creek Parkway and Custer Road intersection was recently completed.
Phase ITimeline: Construction completed
Phase IITimeline: December 2014Cost: $5.2 millionFunding: City of Plano and the North Central Texas Council of Governments
Legacy Drive
Construction will continue for the next few months at Legacy Drive and the Central Expressway frontage road. The project includes building a new on-ramp on the southbound side of the frontage road and removing the stop sign to align traffic with the traffic signal.
Timeline: Construction is expected to be complete by early 2015.
Cost: $65 million
Funding: Texas Department of Transportation
15th Street
Portions of 15th Street will close between 9 a.m. and 4 p.m. to allow crews to remove medians and place temporary asphalt between G Avenue and Central Expressway. This reconstruction will move traffic to the center of the road while crews add a wider sidewalk to the north side of the street.
Timeline: December 2015
Cost: $4 million
Funding: Regional Toll Revenue, Collin County, city of Plano