Completion of Virginia Parkway widening pushed from July to August due to weather

0

Construction on Virginia Parkway has been underway since March 2017 to expand the roadway from four-lanes to six-lanes between Ridge Road and US 75.

Final stages of the project have begun, including paving from Randy Lee Lane to US 75, driveway reconstruction, new signal equipment at Virginia and Randy Lee and the completion of work on Wilson Creek Bridge.

In April, the project’s completion date was pegged for June, but was then pushed to July in May. Now city staff said it will likely be completed in August due to weather delays and franchise utility conflicts.

Virginia is expected to be substantially complete and open to traffic in August.

Other transportation projects can be found here.

Share this story
COMMENT

Leave A Reply

Emily Davis
Emily graduated from Sam Houston State University with a degree in multi-platform journalism and a minor in criminal justice in Spring 2018. During her studies, Emily worked as an editor and reporter at The Houstonian, SHSU's local newspaper. Upon graduation, she began an editorial internship at Community Impact Newspaper in DFW, where she was then hired as Community Impact's first McKinney reporter in August. Three fun facts about Emily: 1.) She is a lover of mystery novels, movies, TV shows and podcasts. 2.) She has an 11-year-old, 3-pound Pomeranian. 3.) She loves lacrosse, and was captain and then coach of her high school team.
Back to top