NorthGate Constructors reported that this project is now 54% complete. Since the start of the new year, crews have opened the new northbound SH 121 auxiliary lanes, which will serve as a new direct connector to FM 2499. In addition, crews have demolished the former northbound FM 2499 bridge to move the project further toward completion, NorthGate spokesperson Maria Woodrow said. In the coming weeks, Woodrow said, the community can expect weekend work to take place as the weather becomes ideal for construction work. Every weekend, utility, structures, paving and roadway teams will continue to perform work throughout various areas of the project.
Timeline: August 2018-2022
Cost: $370 million
Funding source: Texas Department of Transportation