Motorists have been switched onto new northbound pavement on the east side of SH 26 from Brown Trail to Church Street in Colleyville. In addition, vehicles have been moved over onto new pavement on the east side of SH 26 near Glade Road. Old Glade Road has also been reopened to drivers. On the east side of SH 26, construction is ongoing between Brown and Church, with the installation of sidewalks, retaining walls and lighting foundations. Construction is also taking place in the center median areas from Church up north to John McCain Road to remove temporary pavement and build median curbs and left turn lanes. Center median work will be extended south to Brown over the coming weeks.

Timeline: November 2016-spring 2020

Cost: $38.2 million

Funding source: TxDOT