Find out which businesses and renovations are coming to Frisco. The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

Taco Bell: US 380 and Coit Road, Frisco

Type of work: new construction

Timeline: June 1- Nov. 30

Estimated cost: $800,000



Panther Creek Dental: 11020 Panther Creek Parkway, Frisco

Type of work: new construction

Timeline: Feb. 7-May 9

Estimated cost: $222,980


The Shops at Willow Bay Lot 9: Eldorado Parkway and Glacier Drive, Block A, Lot 9, Frisco

Type of work: new construction

Timeline: Feb. 1-Oct. 31

Estimated cost: $3 million


Portoventura Coastal Cuisine: 4606 Frisco Green Ave., Frisco

Type of work: renovation/alteration

Timeline: Jan. 18-May 31

Estimated cost: $700,000


Curry Pizza House Independence: 5353 Independence Parkway, Ste. 105, Frisco

Type of work: renovation/alteration

Timeline: Feb. 1-Oct. 1

Estimated cost: $250,000