Park Boulevard-Independence Parkway repairs
The project to improve the intersection at Park Boulevard and Independence Parkway is nearing completion. Construction to add right-hand turn lanes southbound on Independence Parkway and eastbound on Park Boulevard are expected to be complete by
June 26, followed by sidewalk installations and utility relocations. All work on the intersection is expected to be complete by August.
Timeline: November 2014-August 2015
Cost: $1.9 million
Funding sources: City of Plano, Collin County
Windhaven Parkway widening
Two widening projects along Windhaven Parkway are underway. Construction crews are creating a six-lane divided thoroughfare from Gentle Way to Parkwood Boulevard. Crews are also working on a four-lane widening project on Windhaven Parkway from Parkwood Boulevard to West Spring Creek Parkway. Lane closures will take place during nonpeak hours.
Timeline: June 2015-April 2016
Cost: $3.4 million
Funding sources: City of Plano, Texas Department of Transportation
Midway Road repairs
One northbound lane and one southbound lane along Midway Road from West Spring Creek Parkway to West Parker Road will be closed for concrete repairs. Work is expected to be completed by the end of July, weather permitting. Upon completion of this phase, construction crews will continue the repair work moving southward to Park Boulevard.
Timeline: June - November 2015
Cost: $990,000
Funding sources: City of Plano, Collin County