Completed projects
Neighborhood Street Reconstruction 2
Project: Reconstruct of Great Basin Avenue, Bushmills Road, Picadilly Drive, Pflugerville Loop, Edgemere Drive, Windermere Drive and Yellow Sage Street.
Update: Project is complete
- Timeline: 2020–2025
- Cost: $12.4 million
- Funding Source: certificate of obligation bonds and general obligation bonds
Colorado Sand Drive
Project: The construction of a .53 mile roadway between Copper Mine Drive and Lone Star Ranch Boulevard.
Update: Construction is ongoing and will be complete this year.
- Timeline: 2019–2025
- Cost: $9.9 million
- Funding Source: general obligation bonds and roadway impact fees
Project: This project will widen Kelly Lane from two to four lanes from Falcon Pointe Drive to east of Moorlynch Avenue.
Update: Expected to be completed in summer.
- Timeline: 2019–2025
- Cost: $27.6 million
- Funding Source: certificate of obligation bonds and general obligation bonds
Project: Reconstruction of Grand National Avenue, Rowe Loop, Sullivan Street, Dalshank Street, Algreg Street, Mashburn Street, Option Avenue, Diablo Drive and Butler Drive.
Update: Construction is ongoing and expected to be complete this year.
- Timeline: 2020–2025
- Cost: $6.7 million
- Funding Source: certificate of obligation bonds and general obligation bonds
FM 685
Project: The 2020 General Obligation Bond Program project included a corridor study, preliminary engineering and design. The project includes lane realignment, intersection changes, improvements to shared use paths, right of way acquisition and utility relocation.
Update: The schematic design is 30% complete, and coordination with the Texas Department of Transportation is ongoing.
- Timeline: TBD
- Cost: $175 million
- Funding Source: general obligation bonds and future debt issuance
Project: Construct a four-lane roadway with a center median on Kelly Lane and incorporate four roundabout intersections from Moorlynch Avenue to Weiss Lane. Construction includes curb and gutter, underground storm facilities, pedestrian improvements and street lighting.
Update: Project design is 45% complete and the project is expected to go to bid this summer.
- Timeline: 2020–2029
- Cost: $28.7 million
- Funding Source: certificate of obligation bonds, general obligation bonds and roadway impact fees