What you need to know
Trustees approved three contracts for heating, ventilation and air conditioning at Hutto Elementary School and Hutto High school; a proposal to replace roofing at Farley Middle School and Veteran's Hill Elementary School; and professional design services for the next elementary school. The latter would be slated to open in the fall of 2027, said Dustin Barton, HISD's assistant superintendent of operations.
Between the three contracts, costs total around $5.5 million.
About the projects
Mechanical engineering and commissioning for HVAC replacement at HES and HHS
- Cost: $257,965
- Contractor: Hendrix Consulting Engineers
- Cost: $1.4 million
- Contractor: LD Tebben
- Cost: $960,000
- Contractor: Texas Roofing
- Cost: $2.6 million for the main contract, $225,000 for supplemental services
- Contractor: VLK Architects