The city of New Braunfels began a three- to four-month rehabilitation project on West San Antonio Street on Nov. 18. Affecting San Antonio Street from Academy Avenue to Walnut Avenue, the project will implement roadway and curb repairs that will be done in two phases. Traffic will be transitioned from one side of San Antonio Street to the other in order to allow two-way traffic throughout the duration of the project, according to Jennifer Cain, New Braunfels capital projects manager.
Timeline: November-March
Cost: $800,000
Funding source: city of New Braunfels 2013 bond