Find out more about these projects below, as confirmed by Williamson County officials.
Upcoming projects
1. RM 2243 (Hero Way) Phase 1A
- Project: Reconstruct, realign and widen 3.5 miles of. RM 2243 between 183A and Garey Park in Georgetown to provide a three-lane road with one lane in each direction and a dedicated center turn lane, as well as add a shared-use path for pedestrians and cyclists
- Update: Design is complete, and construction is expected to begin in early 2026
- Timeline: 2026-2028
- Cost: $37 million
- Funding sources: city of Leander, federal funding, Williamson County 2019 road bond
2. Ronald Reagan Widening (Segment B)
- Project: Build a two-lane southbound roadway from Hwy. 29 to FM 3405 and transition the existing road to become northbound only
- Update: Anticipated completion in late 2027
- Timeline: summer 2024-late 2027
- Cost: $53 million
- Funding source: Williamson County 2019 road bond
- Project: Construct a single ramp connecting westbound Hwy. 195 to Ronald Reagan Boulevard
- Update: Williamson County broke ground on the project Aug. 4
- Timeline: summer 2025-summer 2026
- Cost: $3.6 million
- Funding source: Williamson County 2019 road bond
- Project: Construct a new two-lane road alongside the existing road from CR 254 to CR 289
- Update: Williamson County broke ground on the project Feb. 28
- Timeline: early 2025-summer 2026
- Cost: $20.8 million
- Funding source: Williamson County
- Project: Extend CR 110 North from CR 111, which is also called Rockride Lane in Georgetown, to connect with Patriot Way at Sam Houston Avenue, constructing a three-lane interim road
- Update: Anticipated completion in fall 2026
- Timeline: fall 2025-fall 2026
- Cost: $9.4 million
- Funding source: Williamson County 2023 road bond

