Officials with the Union Pacific Railroad company and the city of Oak Ridge North confirmed work to shift the railroad crossing on Robinson Road will begin May 23-25.
The details
According to prior Community Impact reporting, work began on the $7.4 million realignment and widening of Robinson Road in February 2024, and it includes:
- Concrete paving
- Widened roadway
- Realignment of roadway across Hanna Road
As the project nears completion, one of the final steps is to shift the point of crossing for the railroad tracks which runs along Hanna Road. City Manager Heather Neeley said the work being done by UPRR is the first phase of shifting the railroad crossing, and additional work to install the railroad crossing guards and lights will be scheduled at a later date.