David Memorial Drive was previously completed to the Conroe city limits and Houston Methodist The Woodlands Hospital property line, but will now be extended to Hwy. 242 with county road bond money. (Courtesy city of Shenandoah and Montgomery County)
Projects facilitating north-to-south movement in The Woodlands area are seeing forward progress or nearing completion as 2027 approaches, potentially providing relief for commuter roadways such as I-45 and taking the burden off feeder roads and other roadways not meant for heavy thru traffic.
East of I-45, the project to extend David Memorial Drive from Shenandoah to Hwy. 242 that has been planned for over a decade has the green light for completion with $2.5 million in 2025 Montgomery County bond funds from Precinct 4.
Meanwhile, another bond project on the west side of The Woodlands area on Kuykendahl Road will be adding two additional lanes to potentially help reduce congestion between Research Forest Drive and FM 1488.
Both projects could see work begin in 2027.
The big picture
Montgomery County Commissioners Court on Oct. 22 approved plans to complete the David Memorial Drive extension to Hwy. 242, taking over the portion of the project initially slated to be funded by the city of Conroe. The contract was awarded to JFO Services for $1.8 million. An estimated start date has not yet been established for the project.
Shenandoah began construction on the first phase of the project in September 2023. Initially planned to be funded through an interlocal agreement between Shenandoah, Conroe and Montgomery County, the first and second phases of the project from Shenandoah to the Conroe border were completed in July 2024.
The extended David Memorial Drive will cross property owned by Houston Methodist The Woodlands Hospital in the last phase, after right-of-way from the hospital is obtained. Engineer John Bleyl said the value of the right-of-way is $1.5 million.
After Shenandoah completed the first phases of the project, the city of Conroe was not able to budget for construction on the final 1,500 feet within city borders, Community Impact previously reported.
With the $480 million Montgomery County road bond receiving voter approval in May 2025, that project was then folded into the estimated $120 million slated for Montgomery County Precinct 4.
What they're saying
In addition to alleviating congestion on the I-45 feeder, it will also improve emergency response to Houston Methodist The Woodlands Hospital and in Shenandoah, which contracts with The Woodlands Fire Department.
Palmer Buck, fire chief for The Woodlands Fire Department, said the project will help firefighters respond to emergencies more quickly.
“Our Fire Station 6 is located on Windsor Lakes [Boulevard] and has to go all the way down to Research Forest [Drive] to Tamina [Road] south before they can turn back up north to service that east side of [I-]45 in the city,” Buck said. “Right now our units go from Station 1 and [it] takes them a little bit longer because they have to cross over."
Buck said traffic backs up on I-45, noting he expects it will get worse over the next three to five years.
He said the expansion will create better response times for the city of Shenandoah and allow Fire Station No. 6 to have access from Hwy. 242 from David Memorial.
Why it matters
Krystle Riley, chief operating officer of Houston Methodist The Woodlands Hospital, said the extension to Hwy. 242 will improve access for emergency vehicles headed to the hospital.
Annual average daily traffic reports from the Texas Department of Transportation, which track the average number of vehicles that pass a particular location in a day, show an 82% increase from 2021-25 at a point on the I-45 feeder in Shenandoah just south of Ed English Drive, which connects to David Memorial.
"Improved access to our hospital will help patients, families and visitors reach campus more efficiently while providing first responders with another critical route for emergency transport,” Riley said. “As our community continues to grow, infrastructure improvements like this play an important role in ensuring access to high-quality healthcare when and where it is needed most."
As the city of Shenandoah initiated the road extension project more than a decade ago, Shenandoah City Administrator Sam Masiel said officials are excited for its completion. The southern terminus of David Memorial is in an area where the city has seen residential and commercial development at Metropark Square and the Centro community.
“That will help a lot of traffic congestion on the I-45 feeder,” he said. “It has a greater impact than just Shenandoah. … From a mobility standard, it's going to affect everyone, and I think … this is a positive for the county, not just one city, but for everybody.”
Another viewpoint
Other projects in progress in The Woodlands area affecting north-south traffic include a 2025 road bond project to widen Kuykendahl Road from Research Forest Drive to FM 1488 in Precinct 2.
Kuykendahl Road will be widened from two to four lanes, according to information from Precinct 2. The changes will take place in the area around George P. Mitchell Intermediate School, where residents have reported high traffic volumes when school lets out.
However, Precinct 2 Commissioner Charlie Riley said the road project will require new engineering plans that aren’t expected to be complete until February.
“When we first started talking about putting these other two lanes, we thought we could use the old plans,” Riley said. “That ended up not being the case."
Riley said once the plans are approved for the extra two lanes, the precinct can work more quickly to get the contract ready for a bid to begin construction, previously estimated at $8 million.
Public input
Maryann Braid, president of the Village of Alden Bridge in The Woodlands, said she lives near Kuykendahl Road but avoids it due to the backup from school traffic. However, she said some residents are upset about the expansion.
“I am afraid and I think other people are afraid that once they make it four lanes, people are going to use it as a thoroughfare through The Woodlands,” Braid said.
While some residents are concerned about the impact on local roads, Mustafa Tameez, a board member of the Transportation Advocacy Group of Greater Houston, said the projects could give travelers alternative local routes that take the pressure off I-45.
“[This] will improve the quality of life for day-to-day stuff ... [such as] school pickups, going to the grocery store [and] getting to a restaurant in the evening into The Woodlands,” Tameez said of planned projects.
What's next?
Tameez said if officials don’t explore ways to alleviate traffic, future residents will see even greater challenges.
“Having those alternative routes for just going from one neighborhood to the other, have become more and more important ... and if you can do that without getting to I-45 … It's gonna make the daily life better for people long term,” Tameez said.
In addition to the projects planned to reduce congestion on I-45, TxDOT has several projects underway that will further address several locations in The Woodlands area impacted by that roadway.
A project to construct drainage improvements on the I-45 feeder is underway at Shenandoah Park Boulevard to be completed in 2028. The roadway often floods in that area in major rain events, officials have said.
Among other projects planned are the widening of Research Forest Drive and Tamina Road at I-45 to improve congestion at those intersections. Shenandoah funded the design and TxDOT will fund the construction, said John Bleyl, Shenandoah's engineer. A start date for that project has not been set.