1. Maplewood Drive Construction on Maplewood Drive from Ridgewood Drive to Alana Lane in Oak Ridge North, originally planned to be closed to traffic from July 31-Aug. 24, is delayed. The intersection is being reconstructed, and detour routes are posted. The delays are due to rain and water line replacement. Timeline: TBD Cost: $181,000 Funding source: city of Oak Ridge North
2. Kuykendahl Road widening and bridge widening The project includes completion of the widening of Kuykendahl Road from Flintridge Drive to Augusta Pines Drive to four lanes, including building a new two-lane bridge next to the existing bridge over Spring Creek. Additional widening includes Flintridge Drive to Pine Planes Drive and Indian Hills to Timarron neighborhoods, designs of which are both complete. Bid dates for these projects should go out in November. Timeline: TBD Cost: $6.1 million Funding sources: Harris and Montgomery counties, Woodlands Road Utility District
3. I-45 HOV lane extension
The I-45 high-occupancy vehicle lane extension will add one lane in each direction along I-45 from north of FM 1960 to Loop 336 in Conroe. The project was under a delay clause, which allows for further coordination of project details, and construction will begin mid- to late September. The project will be complete the second quarter of 2016, according to The Texas Department of Transportation.
Timeline: September-second quarter of 2016
Cost: $2.6 million
Funding source: TxDOT